TSXV:VER.H - Post by User
Comment by
agilenton Feb 07, 2008 4:03pm
158 Views
Post# 14334739
RE: Contract Link
RE: Contract Linkthx for the 10/10 news
order 523 8/17 $21m to be completed by 9/30/2007
order 573 10/10 $25m to be completed by 6/30/2008
the balance of this 10/10 is still not completed or LM asked to deliver by eof 6/30/2008
now, new anticipated order will be for yr 2009 and beyond or for current yr. i think it will take time.
don't they make other things as well beside these ecms?
future definitely looks good.