Clarification is an understatementShore set out to recover 61,000 tonnes of ore from the underground work at Orion South. To date, they've reported on 14,000 tonnes. Their 08 budget called for $87 million to be spent on Orion South, including the underground work and LDD drilling. Assuming they spent that (I haven't reviewed quarterly reports), they're sitting on tens of thousands of tonnes of ore.
They also now say the underground work is "terminated", not completed. Nor is there any word on percentage of completion, ie recovery of x percent of rock initially targetted. But at the same time, they say they've got enough for a 43101 estimate for Orion South.
One has to stretch the imagination to make sense of it, but good luck to anyone calling IR.