Spud Dates
Spud DatesRecent reply from Brian Adolph - NIKO Country Manager to my question on Qara Dagh Spud dates.
Location construction started in late November 2009 and shall continue to early March 2010.
Rig up will take approx. 2 weeks so a well spud of early April is possible.
Weather in November – March varies with some rain and one or two incidents of snow (1 – 2 days on the ground in the mountains where we will drill). In March the weather is good with spring and summer like conditions. We do not foresee any weather related problems.
Latest news from VST indicates a lilkely slip of 51101 to early January although they have not ruled out issuing it before the Christmas break.
Rumour of merger with LFD seems to have gone quiet both here and on Stockhouse BB. As I have previously posted here, I still think this may be announced before VST spud Qara Dagh.