RE: RE: Long awaited news coming soonUnderground development is progressing, with 410 metres of advance, completed to date. In advance of underground development and mining rehabilitation of the existing ramp, and excavation of a 4.5 metre diameter ventilation raise, were recently completed.Initial mining of ore will be carried out by contractors during the development, with the first ore expected in August 2010. The company plans to mine underground ore, using its own equipment and employees.As development advances, and new equipment arrives, underground production rates are expected to increase to a steady rate of 800 tonnes per day by March 2011. With an expected higher grade +7 grams per tonne average.This will account for 40% of the Black Fox mill designed througput rate. The remaining 60% will be from open pit ore.Further assays are pending from 25 holes. The company plans of adding a third surface drill in Sept 2010. Early in the fourth quarter 2010 the company expects to begin advancing the the 235 m level underground drift at Black Fox to the SE, with this extention of the 235 metre m level drift ,a fourth drill rig will be added.As you can see progress is being made.As always DYODD and good luck to all. Cheers Josa.