RE: RE: Copperwood - another stepHey Rock the UMZ start up delay is due (IMO) to the fact that management changed the origianl plan and decided to build their own Sulfuric Acid plant rather than be reliant on a local supplier. This was originally alluded too in the presentation in Sweden (hosted by OB research) and confirmed in a recent response from management (personal communication).
Lets hope that all goes well this week with start of audit. In the near future start up of UMZ and audit behind us - we should get another serious lift in SP. Then we get to look forward to the new year with hopefully some more good news from Copperwood and EVBC drilling results and of course start of production from EVBC in March/April.