PRODUCTION DelayI posted several days ago about why there is a delay in startup of UMZ. The decision to build their own on site Sulfuric acid plant has put them behind schedule proposed in the original plan - wihich entailed bringing in acid from a supplier.
They have 250,000 tonnes of ore already stock piled and ready for extraction.
As I said before - let us hope for positive results from the audit and then its just a matter of days/weeks before UMZ comes online. Stay positive my friends :-)