Catalysts/ TimeframeIn the latest presentation (December 2010, p.8) they say: "Prefeasibility Study anticipated by Q3/2011"
It's confirmed on page 18:
Q4/2010
Resource Drilling: Monthly drilling results from ongoing drilling; Completion of infill drilling of higher grade zones; Step out drilling underway
Q3-4/2010
Pre-Feasibility: Major contracts awarded for key mine development projects Human Capital: Hiring of key second tier project development managers, mining, process, environmental, community relations and financial
Q1&Q3/2011
Resources: Updates in Q1 & Q3 focused on upgrading resources to M&I Categories and improving definition of the higher grade zones
Q1-3/2011
Mining: Optimizing starter pit design and project cash flow
Q2/2011
Exploration: Initiation of major district-wide new discovery exploration program
Q2-3/2011
Project Design: Optimize surface facility plan; condemnation/geotech drilling
Capex: Refinement analysis to reduce contingency percentage
Q3/2011
Metallurgical: Results of optimization studies of oxide and sulfide deposits
Pre-Feasibility: Completion of oxide Pre-feasibility study
Q3-4/2011
Project Timeline: Potential for fast tracking initial production