Countdown to drilling
Drilling, Testing & Production
-Review bids from drill rig companies - Done
- Select a drilling contractor - on or before February 15, 2011
- Mobilize Rig to drill location - on or before April 15, 2011
- Start drilling - on or before April 30, 2011
- Complete drilling of CS10 - on or before July 15, 2011
- Complete testing of CS10 - on or before August 15, 2011
- Move drill rig to CS11 location - on or before August 30, 2011
- Start drilling CS11 - on or before September 15, 2011
- Complete production facility and start selling CS10 oil - on or before October 30, 2011
- Complete drilling of CS11 - on or before November 30, 2011
- Complete testing of CS11 - on oe before December 31, 2011