LFD Key Dates to have in Mind!
Source - See schedule on LFD presentation on website
Well CS10
- Start drilling - on or before April 30, 2011
- Complete testing of CS10 - on or before August 15, 2011
Well CS11
- Move drill rig to CS11 location - on or before August 30, 2011
- Start drilling CS11 - on or before September 15, 2011
- Complete drilling of CS11 - on or before November 30, 2011
- Complete testing of CS11 - on oe before December 31, 2011
Early Production Facility
- Complete production facility and start selling CS10 oil - on or before October 30, 2011