Conference CallListened to the conference call this morning. Key points:
*
1) SJT1 COD pushed to September 2011. Drilling 2 injection wells in Q2.
*
2) SJT2 COD pushed to Q3 2012 (they're trying to be conservative, it could be earlier).
*
3) Acid wash of SJ9-3 might add 1 to 5 MW. Certification of SJT2 wells is ongoing, will be done in May to July timeframe. Testing is a process, 3 week shutdown of well to let it heat up, and 2 weeks for the long-term test. So after they complete the refork of the final well in May it might take until the first week of July to complete certification. It's ongoing, will unlock lots of money from May through July.
*
4) Orita 4 well 80% of the way to target depth of 14,000 feet.
*
5) John O'Neill definitely a mumbly numbers guy. Anthony Mitchell inspires a lot more confidence.