no production6 months remaining to meet 350000 tonnes
that is 59000 tonnes per month
approx 2000 tonnes per day
keep falling behind , target may not ne meet with only one mining machine
sp dilution coming again in the near future
operating expense per month is 7 million with no revenue
mining conditions may be challenging, thin seam, ground conditions, degassing of seams etc
old mining records clearly show the issues of previous mining on site, CMK may be face d with the same