Production StatusStill worry about production status
Agency still on the web site indicate washplant non producing status
Agency indicate last record of production submitted by client was May 17, 2011 for 117 tonnes for the day with the continious mining machine
A month went by , can anyone confirm status of production, I am wondering if 350 k TONNES will be reachable for the remaining 5 months including a month allowable for machine set-up ug and infrastructure
is there any confirmation that the mining machines are on order
could cmk be in limbo unless management can assure sh that the 350 k is acheivable for this year
i may suspect if not then, management should come out with a new forecast including additional working capital requirements as 7 to 10 million may be used per month for the drivage of the Bates Portal and mine set-up