WOW it took Cameco 4 yr to
WOW it took Cameco 4 yr tocontain flooding. How much did that cost ?
By Christopher Donville - October 23, 2006
Oct.23 (Bloomberg) -- Cameco Corp. was unable to control undergroundflooding at an unfinished uranium mine in Canada, jeopardizing one of therichest deposits of the metal .
``This is a challenging mine,''Grandey said on the first of two conference calls the company heldtoday. Uranium ore atCigar Lake stretches over two kilometers at a deptof 450 meters(1,476 feet), Camceo's said on its Web site.
Cameco resumes drilling at Cigar Lake Sep. 4, 2010)
Camecois back to drilling at Cigar Lake after spending the past four yearsdrying out the flooded underground development.(Prince Albert DailyHerald