Next Steps
Next StepsNext Steps
Q1 2011
- Mobilize concrete contractor
- Begin receiving mining equipment
- Pour first concrete at first of six CCD high rate thickeners
Q2 2011
- Commence surface mine development activities
- Begin receiving long-lead process equipment
- Continue earthworks (total of 5.3 million m3 of surface material being moved)
- Receive initial power generators
Q3 2011
- Complete camp construction (2,500 people)
- Receive first underground mining equipment
- Initiate construction of Marine Terminal
- Initial power plant to become operational
- Commence underground mining
- Commence ROM stockpile & infrastructure
- Plant foundations (crushing, grinding, leach tank, etc.)
- Begin draw down of senior debt
Q4 2011
- Substantial completion of engineering
- Arrival of process plant grinding mills & scrubbers; commence mechanical installation
- Commence tailings dams construction
2012
- Completion of Marine Terminal
- Mechanical completion of copper circuits
2013
- Copper circuit commissioning
- Commence operations
- First copper scheduled late Q1/early Q2
- Copper & zinc sulphate scheduled Q2-Q4