RE: RE: investor relations
From page number 28 at the new presentation:
Update on 2011 drilling program:
1. Drilling activities: Currently, one surface drill rig is at the Skukum Creek area,
a second surface drill rig is at the Goddell area, and a third surface rig is at Mt.
Skukum. Surface drilling will continue until October, 2011.
2. Total depth: Total planned drill meterage between September and October,
2011 is about 9,800 meters.
3. Assay results: Awaiting for assay results of 14 holes from the Skukum Creek
project.
4. Potential high-grade zone: First step out surface drill-hole (Raca 11-01) at
Raca site intercepted 1,280 g/t Ag, 1.9 g/t Au over 1.58 m. (See August 2, 2011
press release for details.)