THE PROGRAM
THE PROGRAM2011 DRILL PROGRAM
2 core rigs 24 hours a day
Drilling rate is approx 100 metres /day
8,200m completed to date, (38holes)
forcasted total approx 9,000 m
PROGRAM GOALS
To confirm mineralization at Prospect Ridge (new deposit)
To extend mineralization into North Block (extension of Mine Ridge)
Stepout mineralization to South (extension of mine Ridge)
To infill orebody in Central block to confirm continuity
To permit Gold Ridge for addional test drilling
NI 43-101 RESOURCE ESTIMATION &3D DEPOPSIT MODEL
Data presently being compiled
METALLURGICAL TESTING
Samples being collected for additional column leach tests on 1.5'' crush material (McCLELLAND LABS)\
12 MONTH ENVIRONMENTAL BASELINE STUDIES
SOIL SAMPLING
In North block (and possibly Prospect Ridge) to assist with drill targeting.
do your own due diligence
herb
being implememented by NORTHWIND ENGINEERING