NAL reports continued improvement at Lochend CardiNAL’s six well Lochend Cardium program continued throughout the third quarter and is exceeding NAL’s internal expectations and type curve. By September 30, 2011, five wells had been drilled with drilling of the sixth well planned for the fourth quarter. Two wells were completed, tied-in and on production during the third quarter, with a combined average September production rate of 325 boe per day for the 8-33-26-3 W5 well (167 boe per day) and 14-20-027-03W5 well (500 boe per day). A further two wells came on production subsequent to quarter end, with first month average rates in the 250 - 500 boe per day range.
https://www.nalenergy.com/files/Q3_2011_report.pdf
-----------