RE: RE: RE: RE: Tehachapi, CA: Winter storm warninFirefighter88, you forgot the sentence after the Dec 31, 2011 date:
"Based on this last rescheduling of the interconnection outage, Western Wind Energy and Windstar contractors RMT (EPC) and Gamesa (WTG) are required to energize and test the Windstar electrical system by December 10th and to complete the entire commissioning of the first 106 MWs by December 31, 2011. Revenue service will happen after December 10th, as the first turbines go online."