windstar update "From: alphaedgeinc@gmail.com [mailto:alphaedgeinc@gmail.com]
Sent: Thursday, February 23, 2012 2:11 PM
Subject: Re: windstar
More than half the turbines at Windstar are now operating and we expect it to be complete in about two weeks or earlier.
Some delays in completion were caused because the local utility, Southern California Edison, had shut down power lines for maintenance and construction for a few weeks. The lines are back on and we are commisioning 2 to 3 turbines per day.
Best regards
Lawrence
Sent on the TELUS Mobility network with BlackBerry"