RE: RE: Estimate The ERCB had requested a response to the SIR#3 by April 13th. Now we have to continue waiting and hope that there are no more information requests required.
SIR#1 submitted August 2011.
SIR#2 submitted Dec 2011.
SIR#3 submitted April 2012.
Seems to be a 4 month interval between requests. Dare we hope for approval by August or earlier?