RE:RE:RE: What a DEAL!!!! Construction of the Boleo process plant and site infrastructure continues on schedule. Critical path analysis of the construction schedule continues to indicate a process plant completion date which is consistent with Baja’s objective of producing copper in the first half of 2013.
At the end of February 2012, construction was 37.2 percent complete with 2,362 people working on the project. We have completed more than 5.8 million cubic meters of earthworks and poured 39,839 cubic metres of concrete. We have commenced theerection of structural steel. Marine terminal construction is also on track, with 67 of 180 piles driven to final acceptance.