Heads Up Was just onsite...........checking out the work
Ball & Sag Mills are about 2 months away (not all equipment is set) and based on work at Gibraltar previously they are about 2 months away from running the Mills IE: Commissioning and troubleshooting
Lots of pipe spools missing, pipelines just started to get tested (not flushed) and few are passing the initial test
They will report that they are commissioning in June and hope to hit commercial by August.
I would say commercial will not be fufilled until October.
I am not a shareholder but thought you might be interested.
The other thing to note, usually you finish the front end first (conveying, Mills, Floatation, ....Thickening, Tailings etc.) and then stagger finish the back end last (Tailings pumps, Tailings Cyclopack Bldg,Tailings Barge)
That way you can commission the front end while back end gets constructed.
Mills are behind (no urgency seen on site for them), Cyclopak steel just went up 2 weeks ago.........need more personnel onsite if they want to complete earlier
Skibum2