EA Applications Timeline...
EA Applications Timeline... From the coalwatch site, They are expecting a Provincial decision early 2012. The Federal decision is expected mid 2013:
https://www.coalwatch.ca/environmental-assessments
Status of the Provincial/Harmonized EA:
On June 7, 2012, the finalized AIR/EISG was published. The proponent will complete its formal application and environmental impact statement and submit it to the EAO.
Compliance Energy stated in a June 7 news release that "Submission of these Applications is expected before year end.”
Once a draft AIR/EIS is accepted by the EAO, it will be posted for public comment. The public comment period will be 50 days, and will be accompanied by public open houses.
07Jun2012: publication of the finalized AIR/EIS Guidelines