Site Update Concentrator shut down for 2 days
was supposed to start-up Saturday am
Normally when you perfom your tests, you run 6 hours, then shutdown
re-align all items due to the thermal and phsical stresses to the equipment.
After realignment, you run for 24 hours.
Onsite they did not stop after 6 hrs to align
trunion bearings are facked now IE: temperature sensors one each side of trunnion, one set were a lot hotter than the other side, vendor was not onsite because the scheduled start-up was later and NGD did not want to pay.
Thursday, everyone onsite NGD employees, received bonus's for early start, and phot-ops with natives took place, everyone congratulating themselves, and falling over each other
It will all come back to bite them
BTW none of the workers were invited for the photo-ops, only the chair swivellers from the office complex
Stay tuned
Skibum2