Production and Development Schedules
Mine production and development have been scheduled for a 22-month period, targeted to commence in 2012, dependant on available finances.
The mine schedule is designed to deliver an average of 205 tonnes of ore per day to an offsite mill over a 22-month period. A summary of the production schedule is shown in the table below.
Milling and Related Costs
Ore will be hauled to surface and placed in a stockpile. The ore will then be crushed to size and loaded into highway haul trucks for transport to an offsite mill facility for further processing and gold/silver recovery.
It is anticipated that the mill charges for the ore processing will include a $50.00 per tonne refining charge, and payment on 95% of the recovered gold and silver. Estimated costs associated with milling and refining of the ore is outlined in the table below.