This is were they at rigth now DEVELOPMENT PATHWAY
Slide 40
Early-stage exploration(May 2008 to June 2011)
•
Explore in, around and below old mine workings in the core mine trend and across the wider property to confirm historical numbers, extend known zones, and make new discoveries -achieved
•
Deliver initial NI 43-101 compliant resource estimation –achieved
Advanced exploration (underway) (Summer 2011 to Spring 2013)
•
Build in-house engineering expertise / team (underway)
•
Prepare internal engineering scoping study (underway)
•
Secure permits to dewater (underway)
•
Underground exploration drill planning (underway)
•
Dewater and rehab shafts & workings (in planning)
•
Upgrade Inferred level resources to M&I with both underground and surface-based drilling
•
Expand resources with underground and surface-based drilling
•
Bulk sample selected zones such as the No. 19 vein
•
Conduct metallurgical test work (commenced)
•
Complete Pre-Feasibility Study (PFS)
Development decision (Summer –Fall 2013)
•
Final Feasibility Study (FS)
•
Mill expansion
•
Production