RE: RE: RE: RE: Conoco news on Canol CP stuff
EL470 Activities
? Construction activities are ongoing, with environmental and wildlife monitors present on site.
? The Mackenzie River crossing should be completed in time for the rig to arrive on January 17.
? The groundwater rig is being prepared for rig mobilization week of January 14, 2013
? The drilling rig is scheduled to arrive in Norman Wells on January 17.
? We expect to set conductor casing on the first well (O-06) on January 14.
? We plan to begin drilling surface hole ("spud" the well) on January 20, depending on weather.
? The camp is expected to be set up and running by January 18.
? Environmental field programs will be starting up in January and early February and will include winter wildlife, surface water and ground water programs