RE: schedule
RE: schedule turbo221: You forgot one important element...... the screening process. Once the Proponent submits the Application/EIS, the CEAA/BCEAO will evaluate the Application/EIS to determine if the Proponent has satisfied all of the requirements,established in the AIR/EIS that were issued by the CEAA/BCEAO to the Proponent in June 2012. IF the requirements are met, the Application will be "accepted" and your timelines would apply. It's my understanding that roughly 50% of Applications don't make it through the screening process the first time, and therefore are not "accepted". The timeline for screening is 30 days, and will be extended if the Application is deemed to have not satisifed all of the requirements. Just a small point of order for those at home keeping score. :)