highlight of the powerpoint presentation
•
Approval of ESHIA filing by the Ethiopian EPA – Q2 2013
•
Grant of mining extraction licence and mine plan by the Ethiopian Ministry of Mines – Q2 2013
•
Letters of commitment from lender syndicate re: debt financing requirements – Q2 2013
•
Sign on with strategic(s) for off-take(s) – Q3 2013
•
EPCM contractor selection – Q3 2013
•
Financial closing – 2H 2013
•
Pre-construction prep work and preliminary engineering field work - Q4 2013
•
Initiate construction - Q4 2013