Stella Production Wells - Ensco 100 Ensco 100 arrived at Teesport on 16 May for a 35 day yard inspection.
With a two day tow to the field, this suggests the first Stella production well will spud around w/c 24 June.
Each production well is conservatively scheduled to take 80 - 90 days to complete - indicating 10.5 - 12 months (mid May 2014 to end June 2014) to complete all four.
The FPF-1 production platform is scheduled to leave the Polish yard and arrive at the Stella field Q1/2014.