RE:RE:43-101 pushed to early November 2013No truth to this mis-statement of fact, that the Resource Estimate is delayed into November
- RPA (formerly Roscoe Postle and Associates Inc.) was hired 18 Jun (Hole 25 in progress) to compile and complete a Mineral Resource Estimate on the Albany Deposit;
- 31 July (Hole 33 in progress) Drill Program on schedule;
- 40 Hole Drill Program to be completed by end August (on schedule); and
- Assays received up to and including Hole 24 (31 July)
IMO, my assumption is that Roscoe (RPA) have been modelling the deposit, plugging the numbers as results come in,… 32 of the 40 holes as of 31 July, assays on 24. (Awaiting Assays West Pipe Holes 26,27, 29-32)
Assaying – Vancouver lab upgrade will reduce turnaround time on assays (previously sent to Brisbane) 18 June NR –
“To date, a total of 3900 samples have been sent to ALS Minerals for graphitic carbon by LECO analyses with results expected soon. The lab is experiencing delays in delivering assay results to Zenyatta related to shipping the large number of samples to Brisbane, Australia for analyses while the Vancouver lab was upgraded. All future samples will now be processed in Vancouver with results released once received.” On schedule for September Mineral Resource Estimate with a minimum 2 additional batches or groupings of West Pipe Assays to come beforehand.
Cheers, Mark