RE:Sustaining Capital: Timing
RE:Sustaining Capital: Timingshermandrock, what am I missing here?
$850 cash costs/ounce
+ (131 - 45 + 19 + 3) / 475K ounces of production in 2014
This comes out to $1,077/ounce. Still producing cash over the course of the year
But I'd argue that the full $131MM of CAPEX this year is cash ($10MM of maintenance and $35MM of stripping are true cash expenditures but are being capitalized) plus a few million of SG&A is stock options.
I get something closer to $1,163/ounce for the year.
I agree with your comment that for a miner with a long-lived project like DGC, you need to look longer term. But given the leverage and the lower than desirable cash position, I think it is appropriate to be concerned about the next couple of quarters.
If you were going to analyze DGC on a quarter-by-quarter basis you need to be aware that 2014 CAPEX will be weighted to the first half of the year while production will be weighted towards 2H. I'm getting all-in costs in the low $1,200s for the first two quarters.