Keephills 1Anyone have an update on Keephills 1 since this note in the 3rd Quarter interim report of ENMAX? Keephills Outage On March 5, 2013, the Keephills Unit 1 generator was removed from service by its operator, Transalta Corporation (Transalta). Keephills Unit 1 provides ENMAX with approximately 340 MW of electricity through a Power Purchase Agreement (PPA). On March 26, 2013, ENMAX received notice from Transalta that it has made a claim of force majeure under the Keephills PPA. Under a force majeure, ENMAX is not compensated for the outage by the operator for the duration of the outage under the terms of the PPA. In addition, during a force majeure, ENMAX is relieved from paying certain capacity charges to the plant owner for the duration of the force majeure event. The Keephills Unit 1 generator returned to service on October 5, 2013. ENMAX and Transalta are in the dispute resolution process in accordance with the terms of the PPA. For the three and nine months ended September 30, 2013, the Keephills outage impact was $51.2 million and $125.1 million, respectively. Resolution of this dispute is not expected to occur during 2013 and any recoveries pursuant to that dispute will be recognized when that dispute is resolved.