RE:Monday - The Big Show.RJ, I am sure the test protocol does not allow them to sandbag the system prior to the 7 day capacity test. All wells should be on line for the 30 day period prior to the required 7 day test. If they are not or cannot be kept on line, the test would either be delayed or run with what they have available. Whether the Nic site shows net or gross is academic, because in either case the plant is not averaging the 60mw needed to prevent default under the loan (according to the company's public filings). The banks have to be at the table in any negotiation to sell the project, or they will ultimately own it. OE