2nd pipeline/Umugini Pipeline
2nd pipeline/Umugini Pipeline29 km are completed & backfilled, the last 2 km more need to be completed. stringing/ welding/coating/ w ray testing are completed on 1/2 of the final 2 km , The fiberoptic cable leak detection system is completed. 23 km of the pipeline have been hydrotested, Pumpng monitoring and controling systems are being finalized.The expected cpmpletion date is somewhere around the end of June 2014. Time to load up