RE:RE:RE:RE:RE:RE:RE:RE:Today's News Ar you confriming that they never supplied 5N from the factory ?
No, I am not able to confirm that 5N left or never left the factory.
I do not know how rapidly the mechanical failure became evident or how many kilos were ever produced.
From my discutions with Kelly before the last two AGMs and what he said during the last AGM I have concluded that the contamination of the HPA1 product was due to the Harper kiln and the inability to produce at 3TPD was due to the flowsheet/equipement design.
Two separate issues with unrelated causes ( not considering the implication of RB ), both have been or are being corrected at the moment.