Previously...Ice Road
MTX had underlain the fact that it could have begun construction of the ice road right up to the first week of February 2014. It had to cancel the bulk sample due to the fact that the Ontario Ministry would not be able to issue the permit in time. Commercial opening for ice roads use usually begins in the first week of every February. Non-commercial use is in December. Metalex Archived News release c. Feb. 20. 2014: U2 Permitting Status " The project description prepared to support a Provincial environmental assessment process for the U2 bulk sample was available for comment until February 10, 2014...Metalex has been advised by the government, that this process will not be complete in time for the project to commence during this winter road season. Unfortunately the bulk sample will now be delayed. "