RE:RE:still needJunoBeach wrote: Page 22 of the following corporate presentation has the plan with the following steps:
1. 200 TpY pilot plant 2016-17
2. 2000 TpY commercial plant 2017-18
3. 2 10k TpY plants 2019-21
Preliminary cost estimates from Pyrogenesis for the 200 TpY pilot was between $3 and $5 million and the 2000 TpY at $15 million (page 23) so they have underestimated the cost as we now know it, but this deal also includes the intellectual property which would be a one time expense.
https://www.uragold.com/wp-content/uploads/2016/05/UBR-Green-Tech-Solar-Silica-PPT-MAY_11_16_V_AMMENDED_FINAL.pdf
It also covers the cost of operating the plant for close to a year as well, it is not far from the original estimate when these two costs are accounted for in fact its just about right on 5 million.