Join today and have your say! It’s FREE!

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Please Try Again
{{ error }}
By providing my email, I consent to receiving investment related electronic messages from Stockhouse.

or

Sign In

Please Try Again
{{ error }}
Password Hint : {{passwordHint}}
Forgot Password?

or

Please Try Again {{ error }}

Send my password

SUCCESS
An email was sent with password retrieval instructions. Please go to the link in the email message to retrieve your password.

Become a member today, It's free!

We will not release or resell your information to third parties without your permission.
Quote  |  Bullboard  |  News  |  Opinion  |  Profile  |  Peers  |  Filings  |  Financials  |  Options  |  Price History  |  Ratios  |  Ownership  |  Insiders  |  Valuation

Painted Pony Pete Ltd PDPYF

"Painted Pony Energy Ltd Petroleum explores, develops, and produces petroleum and natural gas. The company focuses on the development of natural gas and natural gas liquids. The company's operations take place near the Montney formation in Northeast British Columbia. The Montney location is a sweet natural gas-saturated zone (natural gas that does not contain hydrogen sulfide or significant quantities of carbon dioxide) with no associated or underlying water. The company also has multiple gas pr


OTCPK:PDPYF - Post by User

Bullboard Posts
Comment by UppersDownerson Aug 25, 2016 11:32am
140 Views
Post# 25176105

RE:Time Factor (Production Rampup)

RE:Time Factor (Production Rampup)The 2ndQ results answer some of your questions as to production below:


ALTAGAS TOWNSEND FACILITY

The Townsend Facility began producing natural gas sales volumes on July 7, 2016 more than 30 days ahead of Painted Pony's schedule.  The early commissioning of the Townsend Facility has provided Painted Pony the opportunity to accelerate production volume growth in the second half of 2016.  Painted Pony expects raw natural gas production volumes through the Townsend Facility to average over 50 MMcf/d during August 2016; 100 MMcf/d duringSeptember 2016; and 150 MMcf/d during October 2016.  Currently at approximately 50 MMcf/d of production throughput, the Townsend Facility has been performing per expectations with no material operating concerns or deficiencies. Painted Pony continues to anticipate a 2016 year-end exit production rate of approximately 240 MMcfe/d (40,000 boe/d). 

Based on its design, the expected efficiency of the Townsend Facility is anticipated to improve natural gas liquids ("NGL") yields from Blair Creek in addition to allowing for higher production volumes from the liquids-rich Townsend area.  As a result, NGL volumes are expected to increase from approximately 5% of total production volumes currently to approximately 10% of total production volumes in the fourth quarter of 2016.  This will result in a liquids production increase of approximately 300% from current rates of approximately 1,000 bbls/d to an expected year-end production rate of approximately 4,000 bbls/d.  Painted Pony expects the increased NGL production to be comprised of approximately 50% condensate with the remaining volumes to be split evenly between propane and butane. 

Bullboard Posts