RE:Tango hitting on all Cyclinders!Sorry Ace but the production don't start in January 2017 because for the installation of an Autogenous grinding and new granding circuit it take around one year. Tango need to refurbish some installation and need some reconditioned equipment. They will also change or update some equipement in the primary and secondary crushing circuit. You do not start an ore processing plant as easily as you think. It will take a lot of time and energy on the part of employees.