RE:RE:RE:RE:FinancingYou have previously stated that work can't proceed during the winter. According to the 2012 Tetra Tech Report, it was stated that "Wardrop understands that work can largely proceed year round although delays in the winter are a possibility."
The mine location receives up to 1 meter of snow during the winter. That is not enough to prevent access to the site. It will not hinder large earth moving operations. I anticipate we will get a progress report by the end of the calendar year and it will show the mine is being developed for production.