RE:RE:RE:RE:RE:RE:RE:RE:RE:NR pending
RE:RE:RE:RE:RE:RE:RE:RE:RE:NR pendingAll permits are in place for all work. If they do a surface extraction the permit stipulates them to submit a plan on it for approval purposes. They are not changing the quantity of water needed for use. The bulk sample plan was recommended in the resource report and again the pea report. The permit area gave us more detail like location and size of trench and tonnage. Don't think location would ever make it into a NR and maybe the dimensions but probably only the tonnage targets. Pea and resource recommended 400 tonnes. Permit update is 500 tonne target. That is really the only change.
long....pgd....ekim