RE:About the 50 000 tons bulk sample...bossu , my guess for toll milling would be nearby Goldex... here are the plans Integra's mill and transportation 100% reduction ONCE IN OPERATION ...gltal
During the pre-production period, offsite toll milling is planned as tonnage is insufficient to justify starting the Sigma Mill. Transportation (C$4.15/tonne) and milling (C$41-C$43/tonne) quotes from the specific mills identified were used in the cash flow model as well as the expected gold recoveries (89% Triangle and 94.7% Parallel). Transition from toll milling to processing at the Sigma Mill is expected to take place in Q3 of year 2 in the proposed mine plan, at the end of the 18 month pre-production period.