RE:Any update?the Elmworth tie-ins were supposed to be completed by early June. I'd be guessing but commissioning work would need to be done and corrections of any deficiencies prior to startup - then startup would involve opening up of the wells - one at a time - maybe staggered to make sure that the pressure head is off one well and production stabilizing before cracking open the other one. That may take a few days each if things go smoothly. So by AGM time there should be some daily volumes to report on. I'm not sure what the deal is with the Waskahigan well but I didn't think the tie-in of that well would be especially challenging. It would be nice for a pre-AGM status update given how much of a kicking the sp has taken...