RE:RE:RE:RE:RE:Well, time to lighten the Harte load and diversify.FlyingHighAgain wrote: can u post where they say that construction has begun ?thanks
The Company received approval for the construction of the Mill building and installation of principal Mill components including the crushing circuit, ball mill, gravity concentrator, furnace, float concentrate circuit and effluent treatment plant in May 2017 and construction is currently underway. The Company has also submitted a Notice of Material Change regarding an amendment to its Phase 1 Production Closure Plan to provide for on-site milling, the construction of a tailings management facility and full scale commercial production.
This paragraph was taken from the Q2 MDand A document August 14 2017