RE:RE:RE:RE:RE:Vulnerable to M&A according to Scotia...i don't get why Scotio uses a capex of 500 million USD for Timok ... the PEA from the last operator said 200 Million USD...
i can life with 300 millionUSD for an simple DSO-operation for the upper zone... but 500 million is too much....
..this is from the last PEA...
- Pre-production capital of US$213m for Phase 1 starter DSO mine.
- The following capital would be funded from operation cash flow: Phase 2, 1 Mtpa flotation start up capital of US$78m, further sustaining capital of US$149m to increase and maintain production of 2Mtpa (including contingencies at 25%).