Development Design:
• 40 ft. by 12 ft. by 12 ft. timber portal
• Decline will measure 11 ft. high by 10 ft. wide
• Length of decline 610 ft.
• Decline to be driven in at average grade of – 14% for 650 ft. until break-though
into old workings.
• 12 ft. by 12 ft. by 24 ft. muck bays placed every 400 ft.
Expected Development Costs
• USD $2,000,000
Timeline
• Portal – 14 days
• 610 ft of decline development – 45 days
• 2 muck bays – 6 days
Total development time from commencement of work – 65 days
Total cost USD $2,000,000