RE:Road. Email to simon on the review boardUseful email, and thanks. And I can see why mines take foreveeeeeeer... It's sad we're in the home stretch and we still have to wait months and months. Red tape and the rule of law loves incrementalism...
Patience2020 wrote: Hello George,
The Review Board is aiming to release its Report by the end of the month. The Report must get approval from the GNWT and the Tlicho Government. This approval process can take several months.
After the Report is approved by the two governments it will go the Land and Water Board for a land use permit and water licence. Once these permits are approved the project should have the primary approvals it requires.
I hope this helps.
Cheers
-----Original Message-----
From: George <georgemoschop@yahoo.ca>
Sent: March-16-18 7:14 PM
To: Simon Toogood <stoogood@reviewboard.ca>
Subject: EA-1617-01 Tch All Season Road
Hello Simon,
Hope all is well with you and that 2018 has been a great year for you so far!
Just wondering whether the March 30th decision is the Final one for the road. If the EA gives it a green light…how many more steps are there to finalize a 100 percent go on paper to build the road.
Thank you for your time,
George