RE:Feasibility Study??? - Glencore would be responsible for all engineering and technical aspects of the Feasibility Study which is to be delivered nine months from the date of receiving the final assays from the infill drilling program.*1
- A Phase II drill program comprised of approximately 7,500m is scheduled after spring break-up and is intended to target areas of the deposit that can be drill-tested under summer conditions.*2
I would use phase II as a proxy. If it will be done summer or fall? (I dont know when they plan to complete it), expect 9-12 months after that based on the first point. *1 https://www.foranmining.com/news/foran-mining-enters-into-technical-services-agreement-to-advance-mcilvenna-bay
*2 https://www.foranmining.com/assets/docs/FOM-NR%2002%20MAR%202018%20-%20McIlvenna%20Bay%20Drilling%20Update%20-FINAL.pdf