We wanted to provide a quick update on our fabrication progress as well as our EPEA permit. 1. We are pleased that the permitting process continuous to move favorably. We have been in continuous communication with the EPEA and most recently they have stated that we should receive a draft of our permit shortly. 2. Fabrication is progressing on schedule with over 90% of the fabrication being complete. We are extremely excited on progress on all fronts as we are on schedule and budget to have our first continuous flow refinery started by late spring 2018